Meridian Township is requesting proposals for the installation of a new shared use pathway near Newton Road Park in Meridian Township.
Bids are solicited on a unit price basis. The work involves the following major bid items:
- Installation of shared use pathway near Newton Road Park
- Remove and replace damaged shared use pathway at various locations
- Installation of two (2) corrugated steel pipe culverts
Proposals shall include the furnishing of all labor, material, and some equipment to complete the project.
Proposals are due Monday, August 25 by 3:30 pm.
Work on the project must commence within 10 (ten) days of issuance of the “Notice To Proceed.” Construction shall be completed by November 1, 2025. Completion is defined as being constructed, tested, placed in service, and the site restored.
Newton Road Park Pathway 2025 - Contract Book
Newton Road Park Pathway 2025 - Plans