Paving on Sunday, August 30, on Hulett Road was canceled due to rain and has been rescheduled for Monday, August 31.
- August 24: Finish pouring concrete.
- August 25 to August 28: Allow concrete to cure and grade the road to prepare for paving. The road will be graded well prior to the first day of school on Wednesday, August 26.
- August 29 and August 30: Pave the first of two layers of asphalt.
- August 31 to September 5: Restore asphalt and concrete driveways.
Hulett Road will be closed to northbound traffic from Saturday, August 29 to Saturday, September 5. Southbound traffic will be maintained on the side of the road that is not actively being paved.
All school bus routes are southbound only, but the first two paving dates are currently scheduled over a weekend.
Once all driveways have been restored, the Township will announce the two scheduled dates to pave the second and final layer of asphalt on Hulett Road.
After paving is complete, we will construct gravel shoulders, restore grass, apply pavement markings to Hulett Road, install new signage, and adjust mailboxes as needed.