UPDATE (8/26/2026)
The new off-road pathway connecting the Inter Urban Pathway to Haslett Road is now open.
Once a crosswalk can be established at the Haslett Road and Benson Drive intersection, the Township plans to construct a future trail directly north through Hillbrook Park to Lake Lansing Road.
This new off-road pathway was constructed using 775 square yards of steel retaining wall, 520 feet of drain pipe,100 tons of aggregate material, 790 square yards of concrete, and a 37-foot boardwalk.
View the map for this project at the following link: Haslett Road Pathway Construction Schedule Map
UPDATE (2/5/26)
Equipment has been deployed across the Haslett Road corridor to collect traffic and pedestrian counts. The data will be reviewed, and we should have an update regarding our findings in March or April 2026.
Construction of the American House Pathway, an off-road trail, will link the existing Inter-Urban/MSU to Lake Lansing Trail, with the pathway on the south side of Haslett Road at the Benson Drive intersection. Construction began in late 2025 and is anticipated to be completed by June 12, 2026.