2026 Local Roads Program - Curb & Gutter

The 2026 Local Roads Program includes construction on approximately 28 miles of local roadways in Meridian Township. This work is funded by the Local Roads Millage, which was passed by Meridian Township voters in August of 2019. The work ranges from preventative maintenance (to preserve pavement that is still in good condition) to full road reconstruction: 

  • Crack Fill – 20.5 miles
  • Reconstruction of Roads without Curb and Gutter – 3.74 miles
  • Reconstruction of Roads with Curb and Gutter – 3.74 miles
Construction Notices:
2026 Maps:

UPDATE (5/20/26)
Area 4 (Nemoke Trail, Maple Ridge Road, Rolling Hills Drive)

Weather permitting, the Township's concrete contractor will begin curb-and-gutter spot repairs and sidewalk ramp upgrades in this area on 6/1. Weather permitting, the work will take 2-2.5 weeks to complete. 

Before paving work begins, damaged or settled sections of the curb and gutter (that are preventing proper road drainage) will be replaced. The Township will not add additional curb and gutter for replacement, and the Township does not replace curb and gutter for aesthetic purposes.

If the curb and gutter across your driveway is removed, there will be a period when you have to drive over your driveway without the curb and gutter. Once the concrete is scheduled for pouring, Lopez Concrete Construction, LLC will communicate with property owners to ensure their vehicles are moved prior to pouring. The concrete will then take 5-7 days to cure. If concrete is poured across your driveway frontage, you will need to park in the street during this time. 

Additionally, any sidewalks crossing the listed streets on the map above will be upgraded to meet current ADA requirements, as necessary. This generally includes lowering existing sidewalk ramps to reduce ramp slopes, realigning existing ramps to improve directional guidance at the crossing, or adding new ramps to provide an accessible crossing.

Pink paint will be used to mark concrete (curb/sidewalk) for replacement in advance of the concrete contractor mobilizing to each area.

If you have sprinklers, an invisible fence, lighting, landscaping, or any other personal property within approximately 10 feet of any concrete that is marked for replacement, it is recommended that you move these items away from the indicated work so that they are not damaged by the project. Although every effort will be made to avoid damage to personal property items adjacent to the concrete, such as sprinklers, the contractor will not replace or relocate these items except to set them back in, or as close as possible to, their original locations. 

Any items located between the curb and sidewalk are in the public road right-of-way (ROW), not on private property. For areas without sidewalks, the ROW typically extends 33 feet from the road centerline. Placement of items, such as those listed above, in the ROW is subject to permitting and approval by the Ingham County Road Department (ICRD). Damage to any items placed in the ROW without proper permits from the ICRD will not be reimbursed or replaced by Meridian Township.

We're sorry for the inconvenience during construction, and we appreciate your patience as we work to improve your neighborhood and our community.


UPDATE (5/18/26)

Area 4 (Washington Heights Avenue)

The Township currently anticipates closing Washington Heights Avenue to all traffic on Tuesday, May 26. The exact closure date will be subject to weather conditions. The Township will continue to publish construction schedule updates as they are known.

The Washington Heights Avenue closure is expected to last 1-2 weeks. Here is a link to a map showing which drives will be closed and which will remain open during the closure, including a temporary entrance/exit that will be constructed to serve 1804 & 1806 Hamilton Road: Washington Heights Avenue Closure Map.

Weather dependent, work on Washington Heights Avenue is currently scheduled as follows:

  • 5/26: The Township's contractor will lower manholes and build a temporary driveway to serve 1804 & 1806 Hamilton Road while Washington Heights Avenue is open to traffic. Upon completion of this work, Washington Heights Avenue will be closed to all traffic.
  • 5/26-5-29: The Township's contractor will remove existing asphalt, perform a cement stabilization treatment on the gravel base under Washington Heights Avenue, and allow the cement to cure properly before paving work begins.
  • Monday, 6/1: The Township's contractor will pave the first of two layers of asphalt. 
  • Tuesday, 6/2: The Township's contractor will pave the second and final layer of asphalt. The Township's contractor will reopen Washington Heights Avenue in the late afternoon/evening once the asphalt has cured.

The Township's contractor will return in 1-2 weeks to raise manholes with the road open to traffic. Manholes will be raised, and concrete collars will be poured around them. Cones will be placed on the concrete collars while the concrete cures. The contractor will return to remove the cones once the concrete has cured. Please do not drive over the concrete collars until the contractor removes the cones.


UPDATE (5/13/26)
Area 1 (Copperhill Drive and Woodhill Drive) & Area 2 (Stoneycroft Drive and Pebblestone Drive)
 
  • Areas 1 and 2 are fully complete, and the cones around manholes and final traffic control devices just off the road will be collected by 5/16. 
Area 3 (Cornell Woods and Whispering Oaks Neighborhoods)
  • Paving of the first asphalt layer was completed ahead of schedule on 5/12. 
  • Paving of the second and final layer of asphalt will be completed on 5/13, ahead of the neighborhood garage sale scheduled to start on 5/14. 
  • The contractor will return sometime the week of 5/18 to raise manholes after the asphalt has fully cured. Concrete collars will be poured around the manholes after the asphalt has fully cured. Cones will be placed on the concrete collars while the concrete cures. The contractor will return to remove the cones once the concrete has cured. To protect the new concrete, please do not drive over the collars until the contractor removes the cones.
Area 4 (Washington Heights Avenue)
  • Concrete curb-and-gutter spot repairs were completed on 5/12.

Road resurfacing work will begin after Memorial Day. Manholes will be lowered while the road is open to traffic. Washington Heights Avenue will be closed to all traffic during the resurfacing work, which is expected to take 1-2 weeks to complete. The date that the closure is scheduled to begin will be published the week of 5/18.

Please do not go around any barricades. Keeping the road closed to traffic is essential to protecting the structural integrity of the new road and your vehicle. Below is a map showing which drives will be closed and which will remain open during the closure, including a temporary entrance/exit that will be constructed to serve 1804 & 1806 Hamilton Road: Washington Heights Avenue Closure Map.

Once paving is complete, the contractors will reopen Washington Heights Ave to traffic. The contractor will then remove the temporary driveway that served 1804 and 1806 Hamilton Road and raise all manhole structures within the roadway.

We apologize in advance for any inconvenience during construction, and we appreciate your patience and understanding as we work to improve your neighborhood and our community.


UPDATE (5/5/26)

Area 1 (Copperhill Drive and Woodhill Drive)

Weather permitting, the Township’s contractors are scheduled as follows: 

  • 5/8: Manholes will be raised and concrete collars will be poured around them. Cones will be placed on the concrete collars while the concrete cures. The contractor will return to remove cones once the concrete cures. Please do not drive over the concrete collars until the contractor removes the cones.

Area 2 (Stoneycroft Drive and Pebblestone Drive)

Weather permitting, the Township’s contractors are scheduled as follows: 

  • 5/8: Manholes will be raised and concrete collars will be poured around them. Cones will be placed on the concrete collars while the concrete cures. The contractor will return to remove cones once the concrete cures. Please do not drive over the concrete collars until the contractor removes the cones

Area 3 (Cornell Woods and Whispering Oaks Neighborhoods)

Weather permitting, the Township’s contractors are scheduled as follows:  

  • 5/7: Lower all manholes
  • 5/11-5/12: Milling (i.e., removal of existing asphalt)
  • 5/13-5/14: Asphalt Paving

Area 4 (Washington Heights Ave)

Weather permitting, the Township’s concrete contractor will begin replacement of the concrete curb and gutter on 5/7 or 5/8.


UPDATE (4/22/26)

Area 1 (Copperhill Drive and Woodhill Drive)

Weather permitting, the Township’s contractors are scheduled as follows: 
  • 4/23: Pave the first of two layers of asphalt.
  • 4/27: Pave the second and final layer of asphalt.

Manholes will be raised, and concrete collars will be poured around them in 1-2 weeks after the asphalt has fully cured. Cones will be placed on the concrete collars while the concrete cures. The contractor will return to remove the cones once the concrete has cured. Please do not drive over the concrete collars until the contractor removes the cones.

Area 2 (Stoneycroft Drive and Pebblestone Drive)

Weather permitting, the Township’s contractors are scheduled as follows:  

  • 4/24: Pave the first of two layers of asphalt.
  • 4/27: Pave the second and final layer of asphalt.

Manholes will be raised, and concrete collars will be poured around them in 1-2 weeks after the asphalt has fully cured. Cones will be placed on the concrete collars while the concrete cures. The contractor will return to remove the cones once the concrete has cured. Please do not drive over the concrete collars until the contractor removes the cones.

Area 3 (Cornell Woods and Whispering Oaks Neighborhoods)

Replacement of the concrete curb and gutter and sidewalk ramps in Area 3 will begin very soon and should be completed in 1-2 weeks.

The weather-dependent schedule for resurfacing Area 3 will be announced on Friday, April 24.

Area 4 (Washington Heights Ave)

Replacement of the concrete curb and gutter and sidewalk ramps in Area 4 will begin in 1-2 weeks.


UPDATE (3/31/26)

Area 1 (Copperhill Drive and Woodhill Drive)

Replacement of the concrete curb and gutter and sidewalk ramp in Area 1 has begun and should be completed in 1-2 weeks.

Weather permitting, the Township’s contractors are scheduled to resurface Copperhill Dr. and Woodhill Dr. on the following schedule:

  • 4/15-4/17: Lower all manholes
  • 4/20-4/21: Milling (i.e., removal of existing asphalt)
  • 4/22-4/23: Grading and aggregate conditioning to prepare for paving
  • 4/23-4/24: Paving the first of two layers of asphalt
  • 4/24-4/27: Paving the second and final layer of asphalt

Area 2 (Stoneycroft Drive and Pebblestone Drive)

Curb and gutter spot repairs will likely begin the week of April 6 in this area and will take 1-2 weeks to complete.

Weather permitting, the Township’s contractors are scheduled to begin resurfacing Stoneycroft Drive and Pebblestone Drive the week of 4/27 or 5/4.

Please continue to monitor the Township website for construction schedule updates.


UPDATE (3/24/26)

On Thursday, March 26, concrete spot repair work will begin on Copperhill Drive, Woodhill Drive, Stoneycroft Drive, and Pebblebrook Drive. This work will take 1-2 weeks to complete.

Before paving work begins, damaged or settled sections of the curb and gutter (that are preventing proper road drainage) will be replaced. The Township will not add additional curb and gutter for replacement, and the Township does not replace curb and gutter for aesthetic purposes.

If the curb and gutter across your driveway is removed, there will be a period when you have to drive over your driveway without the curb and gutter. Once the concrete is scheduled for pouring, Lopez Concrete Construction, LLC will communicate with property owners to ensure their vehicles are moved prior to pouring. The concrete will then take 5-7 days to cure. If concrete is poured across your driveway frontage, you will need to park in the street during this time. 

Additionally, any sidewalks crossing the listed streets on the map above will be upgraded to meet current ADA requirements, as necessary. This generally includes lowering existing sidewalk ramps to reduce ramp slopes, realigning existing ramps to improve directional guidance at the crossing, or adding new ramps to provide an accessible crossing.

Pink paint will be used to mark concrete (curb/sidewalk) for replacement in advance of the concrete contractor mobilizing to each area.

If you have sprinklers, an invisible fence, lighting, landscaping, or any other personal property within approximately 10 feet of any concrete that is marked for replacement, it is recommended that you move these items away from the indicated work so that they are not damaged by the project. Although every effort will be made to avoid damage to personal property items adjacent to the concrete, such as sprinklers, the contractor will not replace or relocate these items except to set them back in, or as close as possible to, their original locations. 

Any items located between the curb and sidewalk are in the public road right-of-way (ROW), not on private property. For areas without sidewalks, the ROW typically extends 33 feet from the road centerline. Placement of items, such as those listed above, in the ROW is subject to permitting and approval by the Ingham County Road Department (ICRD). Damage to any items placed in the ROW without proper permits from the ICRD will not be reimbursed or replaced by Meridian Township.

We apologize for any inconvenience caused during construction and truly appreciate your patience and understanding as we work to improve your neighborhood and our community.

UPDATE (3/4/26)

Work on the local roads with curb-and-gutter scheduled for resurfacing in 2026 will begin in March 2026 with curb-and-gutter spot repairs (roads shown in green on the map below). Sidewalk and pathway ramps will also be brought into compliance with the Americans with Disabilities Act (ADA). The Township’s concrete contractor is Lopez Concrete Construction, LLC. 

All work on the 2026 local roads with curb and gutter is currently scheduled to occur in the order shown on the following map: 2026 Local Road Program Map with Proposed Work Areas

Work will begin in March when the weather allows. When we can begin pouring concrete depends on the temperatures.

Before paving work begins, damaged or settled sections of the curb and gutter (that are preventing proper road drainage) will be replaced. The Township will not add additional curb and gutter for replacement, and the Township does not replace curb and gutter for aesthetic purposes.

If the curb and gutter across your driveway is removed, there will be a period when you have to drive over your driveway without the curb and gutter. Once the concrete is scheduled for pouring, Lopez Concrete Construction, LLC will communicate with property owners to ensure their vehicles are moved prior to pouring. The concrete will then take 5-7 days to cure. If concrete is poured across your driveway frontage, you will need to park in the street during this time. 

Additionally, any sidewalks crossing the listed streets on the map above will be upgraded to meet current ADA requirements, as necessary. This generally includes lowering existing sidewalk ramps to reduce ramp slopes, realigning existing ramps to improve directional guidance at the crossing, or adding new ramps to provide an accessible crossing.

We apologize for any inconvenience caused during construction, and we truly appreciate your patience and understanding while we work to improve your neighborhood and our community.

For Meridian Township's road classification map, the 2019 PASER rating map, and the 2025 post-construction PASER rating map, please view the three links below:

 

Contact Us

517.853.4440
dpw@meridian.mi.us

Water & Sewer Emergencies:
517.853.4911

5151 Marsh Road
Okemos, MI 48864