UPDATE 6/27/25
All of the roads scheduled for asphalt rejuvenator treatments on June 24 were completed on schedule with the exception of River Terrace Drive and Huron Hill Drive.
River Terrace Drive and Huron Hill Drive were treated on Friday, June 27.
Overglen Court was also treated on Friday, June 27.
Due to the rain events from June 25-27, the schedule for all remaining treatment dates was moved back 2-3 days.
An updated schedule of the treatment can be found below:
Meridian Township Asphalt Rejuvenator Schedule
UPDATE 6/26/25
All of the roads scheduled for asphalt rejuvenator treatments on June 24 were completed on schedule with the exception of River Terrace Dr and Huron Hill Dr. Weather permitting, River Terrace Dr and Huron Hill Dr will be treated on Friday, June 26.
Due to the rain events on June 25 and 26, the schedule for all remaining treatment dates was moved back two days.
An updated schedule of the treatment can be found below:
Meridian Township Asphalt Rejuvenator Schedule
UPDATE 6/25/25
The roads scheduled for asphalt rejuvenator treatments on June 24 were completed on schedule. The contractor will return in on June 26 or 27 to sweep these streets clean.
Due to the rain events on June 25, the schedule for all remaining treatment dates was moved back one day.
An updated schedule of the treatment can be found below:
Meridian Township Asphalt Rejuvenator Schedule
UPDATE 6/10/25
Beginning Tuesday, June 24, an asphalt rejuvenator treatment will start being applied to the roads listed in the Asphalt Rejuvenator Resident Notice.
The purpose of an asphalt rejuvenator is to reverse the effects of deterioration caused by sunlight and water on the pavement, thereby delaying future decline.
A tentative schedule of the treatment can be found below:
Meridian Township Asphalt Rejuventor Schedule
For questions, please contact dpw@meridian.mi.us.